End of Lease Make Good Sydney The Mistakes That Cost Tenants Thousands

Most tenants read their lease once at signing. The make-good clause is usually buried somewhere around page 47. By the time it matters, it is too late to negotiate it.

That is the problem. Make-good obligations in commercial leases can run to tens of thousands of dollars in required works. And if those works are not completed to the landlord’s satisfaction before the lease expires, the bank guarantee is at risk. In Sydney, commercial bank guarantees are typically set at three to six months of gross rent. For a mid-size office tenancy, that is a six-figure sum the landlord can draw on without going to court.

This article covers what your make-good clause actually requires, what a schedule of dilapidations is and how to respond to one, the five mistakes that consistently cost Sydney tenants money, and how to manage the final inspection without it turning into a dispute.

Key Takeaways

  • There are five common make-good clause types in Sydney commercial leases. Each requires something different. Knowing which one you have changes everything.
  • “At landlord’s election” is the riskiest clause language. It gives the landlord the choice between requiring works or claiming a cash equivalent and often at an inflated figure.
  • A schedule of dilapidations must be responded to in writing, item by item, within the timeframe in your lease. Silence is not a defence.
  • Not having a condition report from lease commencement is the single most damaging mistake a tenant can make. Without it, you cannot contest what was pre-existing.
  • Allow a minimum of 6 to 8 weeks from lease expiry to start make-good works. Most tenants underestimate the time required.
  • Verbal agreements with property managers are not binding. Everything must be confirmed in writing by an authorised representative of the landlord.

How to Read Your Commercial Make-Good Clause

Not all make-good clauses require the same thing. There are five common types used in Sydney commercial leases. The type you have determines the scope of work, the standard required, and your exposure if you get it wrong.

1. Return to Original Condition

The most onerous type. You are required to restore the premises to the exact condition they were in at lease commencement — every partition removed, every finish reinstated, every alteration reversed. A detailed condition report and photos from day one of the lease are essential for this clause type. Without them, you have no reference point and the landlord’s version of “original condition” becomes the only version.

2. Back to Base Building

Requires the tenant to remove all fitout and restore the space to the base building specification — as it was when the building was originally completed by the developer. This is different from “original condition” if the tenancy had a prior fitout in place when you moved in. Check the base building drawings carefully. Items from the previous tenant’s fitout that you inherited may or may not be yours to remove.

3. Strip-Out Only

Remove the tenant’s fitout. No requirement to reinstate finishes or restore to any particular standard. This is the most favourable clause type for tenants. But “strip-out” still needs to be interpreted against the base building drawings — removing something that was already there is still a breach.

4. Make Good at Landlord’s Election

The most commercially dangerous clause type. The landlord has the right to choose whether to require the tenant to physically complete the make-good works, or to accept a cash payment equivalent to the estimated cost of those works. Landlords regularly elect the cash option and claim amounts that exceed what the actual work would have cost. If your lease contains this language, get legal advice before your lease expiry date — not after.

5. Make Good as Agreed

Works are defined in a schedule agreed between the landlord and tenant, either at commencement or during the lease term. The clearest and most protective option for tenants — provided the agreed scope is thorough and documented properly. If the schedule is vague, it creates the same problems as any other clause type.

Red Flag Language to Watch For

  • “At landlord’s election”: As described above, this removes your ability to control the outcome.
  • “Fair presentation”: An undefined standard. Landlords interpret it broadly. Ask your solicitor to define it before you rely on it.
  • “Reasonable condition”: Similarly undefined. What is reasonable to a tenant and what is reasonable to a landlord are rarely the same thing.

If your clause is ambiguous, specific questions to raise with a solicitor include: does this clause apply to items that were in the tenancy before my lease commenced, who determines what the “base building” standard means, and does my maintenance obligation differ from my make-good obligation under this lease?

For the physical execution of defit and make-good works, including services isolation, strip-out sequencing, and close-out documentation, see our guide to professional office and shop defits in Sydney.


What a Schedule of Dilapidations Is and How to Handle It

A schedule of dilapidations is a formal document prepared by the landlord or their building consultant — typically a quantity surveyor or property consultant — that lists alleged breaches of the tenant’s maintenance and make-good obligations under the lease. It is the landlord’s itemised claim.

When to Request It

Do not wait for the landlord to send it. Request the schedule 6 to 12 months before your lease expiry date. This gives you enough time to review it, gather evidence for items you intend to dispute, obtain quotes for items you accept, and programme the works. Tenants who receive a schedule four weeks before expiry have almost no room to move.

How to Review It

Cross-reference every item in the schedule against two documents: your lease commencement condition report and the base building drawings. These are your primary evidence sources. For each item claimed, ask: was this condition pre-existing at lease commencement, is this item part of the base building or part of my fitout, and does my lease actually require me to address this?

How to Respond

Always respond in writing within the timeframe specified in your lease. Go through the schedule item by item. For each item, either accept it and confirm your intention to address it, or formally dispute it with the specific evidence supporting your position. A blanket “we dispute the schedule” without item-by-item responses is not sufficient and may be treated as non-response.

What Landlords Sometimes Add

It is not unusual for a schedule to include items that were pre-existing at commencement, items that constitute fair wear and tear, or maintenance items that are arguably the landlord’s responsibility under the lease. Check each one. Not everything on the schedule is necessarily your obligation.


Five Mistakes That Consistently Cost Sydney Tenants Money

Mistake 1: Assuming Fair Wear and Tear Covers More Than It Does

Fair wear and tear in a commercial lease covers gradual deterioration from ordinary, intended use over the lease term. It does not cover damage, neglect, alterations, or deterioration caused by anything beyond normal occupation. Carpet worn down by foot traffic over five years: likely fair wear and tear. Carpet damaged by a furniture move: not covered. Wall marks from a whiteboard mounted without proper backing: not covered. Landlords know where the line is. Many tenants don’t, and they accept liability for items they could have successfully disputed.

Mistake 2: No Condition Report from Lease Commencement

Without a condition report documenting the state of the premises at lease start, you have no evidence for disputes about what was pre-existing. If the landlord claims the kitchen benchtop was damaged during your tenancy and you have no photos from day one, you cannot prove it was already like that. This is the single most consequential oversight in make-good disputes. If your lease has already started and you don’t have one, photograph and document everything now while you still have the opportunity.

Mistake 3: Starting Too Late

Four weeks before lease expiry is not enough time. Strip-out takes 1 to 3 working days, patch and paint takes 2 to 5 days, carpet takes 1 to 2 days, final clean takes 1 day. That is potentially two working weeks for the works alone. Then add landlord inspection notice time (typically 5 to 10 business days), plus the possibility of a re-inspection if defects are found. You can be looking at 6 to 8 weeks from go to completion. Starting late almost always produces holdover rent exposure. And holdover in a Sydney commercial lease activates at 150% of base rent.

Mistake 4: Ignoring the Base Building Drawings

Tenants regularly remove items during a defit that they believe are part of their fitout — but are actually base building. Lighting grids, certain mechanical components, structural partitions, base building data cabling. Removing these items creates a reinstatement obligation that is typically expensive to rectify. Obtain the base building drawings from your landlord or building manager and check them against your fitout plans before any work starts. If you never received base building drawings, request them now.

Mistake 5: Trusting Verbal Agreements with Property Managers

Property managers are not always authorised to make binding commitments on behalf of the landlord entity. “The property manager said we don’t need to do the kitchen” is not a defence when the landlord’s solicitor issues a claim. Every agreement, concession, or variation to make-good scope must be in writing, signed by an authorised representative of the landlord, and retained. If a property manager tells you something verbally, follow up with a written email confirming what was said and ask them to confirm it in writing. If they won’t confirm it in writing, assume it doesn’t exist.


Working Backwards from Your Lease Expiry Date

Make-good always takes longer than tenants expect. Here is a realistic timeline for a standard Sydney commercial office tenancy of 300 to 500 square metres:

Make-Good Task Realistic Duration
Strip-out of tenant fitout 1 to 3 working days
Patching and painting 2 to 5 working days
Carpet replacement (if required) 1 to 2 working days
Final commercial clean 1 working day
Landlord inspection notice period 5 to 10 business days
Re-inspection (if defects found) Add 1 to 2 weeks
Minimum total buffer from expiry 6 weeks (8 weeks if scope is uncertain)

Work backwards from your lease expiry date. If expiry is 30 June, make-good works should start no later than mid-May for a standard scope. If the scope is unclear or a schedule of dilapidations has not yet been received and agreed, start in early May.

If this timeline is not met, holdover rent activates at 150% of base rent. The daily financial cost of a delayed make-good — and how to calculate your specific exposure — is covered in our guide to commercial defit costs and holdover rent in Sydney.


Handling the Final Inspection and Managing Disputes

What to Prepare Before the Inspection

Prepare a complete documentation pack before the landlord’s representative arrives. This should include photographs of all completed works, contractor invoices and sign-off records, any required services isolation certificates, and as-built drawings if the scope included services work. This is your evidence file. If a dispute arises, these documents are what you rely on.

How to Present the Site

Present the tenancy in the same order the schedule of dilapidations listed items. Walk through it methodically with the landlord’s representative. For each item they flagged, show the completed work or the evidence that the item was pre-existing or not your obligation. A structured walkthrough is harder to dispute than a general impression.

What to Contest and How

If the landlord’s representative raises items at inspection that you dispute, do not agree verbally. Take notes. After the inspection, respond in writing with your position on each disputed item, the specific lease clause you are relying on, and the supporting evidence. Evidence that supports a successful contest includes lease commencement condition report photos, base building drawings confirming an item is base building not fitout, and the lease clause itself where the obligation claimed is not actually in the document.

The NCAT Pathway

For retail leases under the NSW Retail Leases Act 1994, unresolved disputes can be referred to the NSW Civil and Administrative Tribunal (NCAT). The process involves lodging an application, attending mediation, and if not resolved, a formal hearing. For non-retail commercial leases, disputes typically proceed through the courts depending on the amount in dispute. In both cases, engage a commercial property solicitor before taking any formal steps. The cost of getting the process wrong can exceed the cost of the original dispute.

What Landlords Cannot Claim

Even where a breach exists, a landlord’s recovery is not uncapped. Claims are typically limited to the reasonable cost of rectification and any proven financial loss directly caused by the breach. Landlords cannot claim betterment, meaning they cannot require you to fund an upgrade to a higher standard than what existed before your tenancy. They also cannot claim for loss of rent during a rectification period unless the lease specifically provides for it. Knowing these limits matters when evaluating whether to accept a claim or contest it.

Not Sure What Your Make-Good Clause Actually Requires?

Our team can review your lease scope, walk through the dilapidations schedule with you, and give you a clear picture of what the make-good work involves, how long it will take, and what it will cost. Get ahead of your expiry date before the timeline gets tight.

Request a Lease and Dilapidation Review Consultation

Frequently Asked Questions

Make good refers to the tenant’s obligation at the end of a commercial lease to return the premises to a specified condition. Depending on the clause type, this can mean removing all fitout and restoring base building finishes, strip-out only, or a defined scope agreed between the parties. The standard required varies significantly between leases, which is why reading and understanding your specific clause is essential before any work is planned.
Costs vary depending on the size of the tenancy, the fitout complexity, and the scope required under the lease. For a standard 300 to 500 square metre Sydney CBD office, a full make-good including strip-out, patching, painting, carpet, and final clean typically runs $15,000 to $45,000. Tenancies with significant fitout, services modifications, or “return to original condition” clauses can run higher. A site inspection with a qualified defit contractor will give you a fixed price based on your actual scope.
It depends on your lease clause and the condition of the carpet. If the clause requires you to return the premises in a specified condition and the carpet is damaged beyond fair wear and tear, replacement is likely required. If the carpet is simply worn from normal use over a long lease term, fair wear and tear may apply. Check your lease clause, review your commencement condition report, and get a professional opinion on the carpet condition before committing to a position.
A schedule of dilapidations is the landlord’s itemised list of alleged breaches of your maintenance and make-good obligations. You are not required to accept every item on it. Each item should be reviewed against your lease, your commencement condition report, and the base building drawings. Items that are pre-existing, constitute fair wear and tear, or are not covered by your lease obligations can be formally disputed in writing.
Start the planning process 6 to 12 months before expiry. Request the schedule of dilapidations early. Commission quotes from qualified contractors. Allow a minimum of 6 weeks before expiry to complete the works, with landlord inspection and re-inspection buffer included. If the scope is unclear or complex, start earlier. Waiting until 4 to 6 weeks before expiry almost always creates timeline pressure that leads to holdover rent exposure.
A landlord must release the bank guarantee once all lease obligations are met and the make-good is accepted. If the landlord delays without legitimate cause, you have grounds to demand release in writing and, if necessary, pursue the matter through legal channels. Document the completion of works thoroughly-contractor invoices, inspection records, written communications, so your position is clearly evidenced if the release is disputed.
A defit (defitout) refers to the physical removal of a tenant’s fitout. Make good is the broader lease obligation that may include the defit plus reinstatement of finishes, painting, carpet, cleaning, and services restoration. Not every make good requires a full defit. A “strip-out only” clause may just require the defit. A “return to original condition” clause will require the defit plus significant reinstatement work beyond it.
It means restoring the tenancy to the condition the building was in when it was first completed by the developer, before any tenant fitout was installed. This is defined by the base building drawings, which show the base mechanical, electrical, hydraulic, and fire systems, as well as the base finishes. Anything the tenant added beyond that standard must be removed or restored. Obtain and check those drawings — they are the reference point for every dispute about what stays and what goes.
Yes, but the time to negotiate is well before the lease expires, not in the final weeks. Many landlords are open to agreeing a defined scope, accepting a cash settlement in lieu of works, or agreeing to waive certain items if the space is being re-leased with a new fitout immediately. These conversations are far easier to have 6 to 12 months before expiry when both parties have time and leverage is balanced. Any agreed variation must be documented in writing and signed by an authorised representative of the landlord.
Returning the keys does not end the make-good obligation. If the inspection fails, the landlord can require rectification and holdover provisions may continue to apply until the make-good is accepted. Keep a copy of all access credentials and contractor contacts until the bank guarantee is formally released and the landlord provides written confirmation of scope completion. Do not assume that handing back keys is the finish line.

Disclaimer: The information in this article is based on research and the professional experience of the Get It Away Demolition and Excavations team. Nothing in this article constitutes legal advice. Make-good obligations vary significantly between individual leases, building types, and commercial arrangements. For advice specific to your lease, engage a qualified commercial property solicitor. Cost figures reflect general Sydney market conditions as of 2025 and will vary based on tenancy size, scope, and contractor pricing.

Leave a Comment

Your email address will not be published. Required fields are marked *

Scroll to Top