End of Lease Make Good Sydney: The Mistakes That Cost Tenants Thousands
Most tenants read their lease once at signing. The make-good clause is usually buried somewhere around page 47. By the time it matters, it is too late to negotiate it.
That is the problem. Make-good obligations in commercial leases can run to tens of thousands of dollars in required works. And if those works are not completed to the landlord’s satisfaction before the lease expires, the bank guarantee is at risk. In Sydney, commercial bank guarantees are typically set at three to six months of gross rent. For a mid-size office or a large warehouse, that is a six-figure sum the landlord can draw on without going to court.
This article covers what your make-good clause actually requires, what a schedule of dilapidations is and how to respond to one, the five mistakes that consistently cost Sydney tenants money, and how to manage the final inspection without it turning into a dispute.
Key Takeaways
- There are five common make-good clause types in Sydney commercial leases. Each requires something different. Knowing which one you have changes everything.
- “At landlord’s election” is the riskiest clause language. It gives the landlord the choice between requiring works or claiming a cash equivalent and often at an inflated figure.
- A schedule of dilapidations must be responded to in writing, item by item, within the timeframe in your lease. Silence is not a defence.
- Not having a condition report from lease commencement is the single most damaging mistake a tenant can make. Without it, you cannot contest what was pre-existing.
- Allow a minimum of 6 to 8 weeks from lease expiry to start make-good works. Most tenants underestimate the time required.
- Warehouse and factory make goods take longer than offices. Racking, mezzanines, slab repairs, plant services, asbestos and possible contamination all need to be scoped early.
- Verbal agreements with property managers are not binding. Everything must be confirmed in writing by an authorised representative of the landlord.
How to Read Your Commercial Make-Good Clause
Not all make-good clauses require the same thing. There are five common types used in Sydney commercial leases. The type you have determines the scope of work, the standard required, and your exposure if you get it wrong.
1. Return to Original Condition
The most onerous type. You are required to restore the premises to the exact condition they were in at lease commencement. That means every partition removed, every finish reinstated and every alteration reversed. A detailed condition report and photos from day one of the lease are essential for this clause type. Without them, you have no reference point and the landlord’s version of “original condition” becomes the only version.
2. Back to Base Building
Requires the tenant to remove all fitout and restore the space to the base building specification, meaning the space as it was when the developer first completed the building. This is different from “original condition” if the tenancy had a prior fitout in place when you moved in. Check the base building drawings carefully. Items from the previous tenant’s fitout that you inherited may or may not be yours to remove.
3. Strip-Out Only
Remove the tenant’s fitout. No requirement to reinstate finishes or restore to any particular standard. This is the most favourable clause type for tenants. But “strip-out” still needs to be interpreted against the base building drawings. Removing something that was already there is still a breach.
4. Make Good at Landlord’s Election
The most commercially dangerous clause type. The landlord has the right to choose whether to require the tenant to physically complete the make-good works, or to accept a cash payment equivalent to the estimated cost of those works. Landlords regularly elect the cash option and claim amounts that exceed what the actual work would have cost. If your lease contains this language, get legal advice before your lease expiry date, not after.
5. Make Good as Agreed
Works are defined in a schedule agreed between the landlord and tenant, either at commencement or during the lease term. The clearest and most protective option for tenants, as long as the agreed scope is thorough and properly documented. If the schedule is vague, it creates the same problems as any other clause type.
Red Flag Language to Watch For
- “At landlord’s election”: As described above, this removes your ability to control the outcome.
- “Fair presentation”: An undefined standard. Landlords interpret it broadly. Ask your solicitor to define it before you rely on it.
- “Reasonable condition”: Similarly undefined. What is reasonable to a tenant and what is reasonable to a landlord are rarely the same thing.
If your clause is ambiguous, specific questions to raise with a solicitor include: does this clause apply to items that were in the tenancy before my lease commenced, who determines what the “base building” standard means, and does my maintenance obligation differ from my make-good obligation under this lease?
For the physical execution of defit and make-good works, including services isolation, strip-out sequencing, and close-out documentation, see our guide to professional office and shop defits in Sydney.
What a Schedule of Dilapidations Is and How to Handle It
A schedule of dilapidations is a formal document prepared by the landlord or their building consultant, typically a quantity surveyor or property consultant. It lists alleged breaches of the tenant’s maintenance and make-good obligations under the lease. It is the landlord’s itemised claim.
When to Request It
Do not wait for the landlord to send it. Request the schedule 6 to 12 months before your lease expiry date. This gives you enough time to review it, gather evidence for items you intend to dispute, obtain quotes for items you accept, and programme the works. Tenants who receive a schedule four weeks before expiry have almost no room to move.
How to Review It
Cross-reference every item in the schedule against two documents: your lease commencement condition report and the base building drawings. These are your primary evidence sources. For each item claimed, ask: was this condition pre-existing at lease commencement, is this item part of the base building or part of my fitout, and does my lease actually require me to address this?
How to Respond
Always respond in writing within the timeframe specified in your lease. Go through the schedule item by item. For each item, either accept it and confirm your intention to address it, or formally dispute it with the specific evidence supporting your position. A blanket “we dispute the schedule” without item-by-item responses is not sufficient and may be treated as non-response.
What Landlords Sometimes Add
It is not unusual for a schedule to include items that were pre-existing at commencement, items that constitute fair wear and tear, or maintenance items that are arguably the landlord’s responsibility under the lease. Check each one. Not everything on the schedule is necessarily your obligation.
Five Mistakes That Consistently Cost Sydney Tenants Money
Mistake 1: Assuming Fair Wear and Tear Covers More Than It Does
Fair wear and tear in a commercial lease covers gradual deterioration from ordinary, intended use over the lease term. It does not cover damage, neglect, alterations, or deterioration caused by anything beyond normal occupation. Carpet worn down by foot traffic over five years: likely fair wear and tear. Carpet damaged by a furniture move: not covered. Wall marks from a whiteboard mounted without proper backing: not covered. Landlords know where the line is. Many tenants don’t, and they accept liability for items they could have successfully disputed.
Mistake 2: No Condition Report from Lease Commencement
Without a condition report documenting the state of the premises at lease start, you have no evidence for disputes about what was pre-existing. If the landlord claims the kitchen benchtop was damaged during your tenancy and you have no photos from day one, you cannot prove it was already like that. This is the single most consequential oversight in make-good disputes. If your lease has already started and you don’t have one, photograph and document everything now while you still have the opportunity. On industrial sites the same applies to the ground. A baseline environmental report from the start of the lease is your evidence if the landlord later claims contamination.
Mistake 3: Starting Too Late
Four weeks before lease expiry is not enough time. Strip-out takes 1 to 3 working days, patch and paint takes 2 to 5 days, carpet takes 1 to 2 days, final clean takes 1 day. That is potentially two working weeks for the works alone. Then add landlord inspection notice time (typically 5 to 10 business days), plus the possibility of a re-inspection if defects are found. You can be looking at 6 to 8 weeks from go to completion. Starting late almost always creates holdover rent exposure. Many Sydney commercial leases set holdover rent at 150% of base rent, so check what yours says.
Mistake 4: Ignoring the Base Building Drawings
Tenants regularly remove items during a defit that they believe are part of their fitout but are actually base building. Lighting grids, certain mechanical components, structural partitions, base building data cabling. Removing these items creates a reinstatement obligation that is typically expensive to rectify. Obtain the base building drawings from your landlord or building manager and check them against your fitout plans before any work starts. If you never received base building drawings, request them now.
Mistake 5: Trusting Verbal Agreements with Property Managers
Property managers are not always authorised to make binding commitments on behalf of the landlord entity. “The property manager said we don’t need to do the kitchen” is not a defence when the landlord’s solicitor issues a claim. Every agreement, concession, or variation to make-good scope must be in writing, signed by an authorised representative of the landlord, and retained. If a property manager tells you something verbally, follow up with a written email confirming what was said and ask them to confirm it in writing. If they won’t confirm it in writing, assume it doesn’t exist.
Working Backwards from Your Lease Expiry Date
Make-good always takes longer than tenants expect. Here is a realistic timeline for a standard Sydney commercial office tenancy of 300 to 500 square metres:
| Make-Good Task | Realistic Duration |
|---|---|
| Strip-out of tenant fitout | 1 to 3 working days |
| Patching and painting | 2 to 5 working days |
| Carpet replacement (if required) | 1 to 2 working days |
| Final commercial clean | 1 working day |
| Landlord inspection notice period | 5 to 10 business days |
| Re-inspection (if defects found) | Add 1 to 2 weeks |
| Minimum total buffer from expiry | 6 weeks (8 weeks if scope is uncertain) |
Work backwards from your lease expiry date. If expiry is 30 June, make-good works should start no later than mid-May for a standard scope. If the scope is unclear or a schedule of dilapidations has not yet been received and agreed, start in early May.
These durations are for an office. A warehouse or factory with racking, mezzanines and plant will take longer, for the reasons in the next section.
If this timeline slips, holdover rent kicks in. In many Sydney leases that is 150% of base rent. The daily cost of a delayed make good, and how to work out your own exposure, is covered in our guide to commercial defit costs and holdover rent in Sydney.
Make Good for Warehouses and Factories
Industrial make goods follow the same lease rules as an office. The scope is what changes. You are dealing with heavy items fixed into the slab, services that run to plant, and in older buildings, materials that need a licensed contractor to remove.
Check each item below against your lease and the base building drawings before you price anything.
| Item | What the Lease Usually Requires | What to Check |
|---|---|---|
| Pallet racking | Removal of all racking, with anchor bolts cut flush or removed and the holes patched. | Who installed it. Racking left by a previous tenant may or may not be yours to remove. |
| Mezzanines | Removal of the structure, stairs and handrails, and repair of the floor and any services below. | Whether it is base building or tenant fitout. Some mezzanines were approved as part of the building. |
| Warehouse slab | Repair of damage beyond fair wear and tear, such as broken joints, chipped edges and core holes. | Oil and chemical staining, tenant line marking, and whether the lease asks for the slab to be cleaned or resealed. |
| Dock levellers, roller doors and bollards | Repair or removal of anything the tenant installed or damaged. | Forklift damage to door tracks, columns and kerbs is rarely accepted as fair wear and tear. |
| High-bay lighting and power drops | Removal of tenant-installed lights, power drops and switchboard additions, made safe by a licensed electrician. | Which fittings are base building. Removing base building lighting creates a reinstatement cost. |
| Compressed air, gas and process lines | Disconnection, capping and removal back to the point agreed in the lease. | Isolation certificates for every service. Your inspection pack should include them. |
| Spray booths, dust extraction and plant | Removal of equipment, ducting, roof penetrations and plant footings. | Residue in ducts and filters may need specialist handling and disposal. |
| Pits, interceptors and trade waste | Cleaning and handover in working order, or decommissioning if the lease requires it. | If you hold a trade waste agreement with Sydney Water, check what needs to happen to it when you leave. |
| Signage and hardstand | Removal of tenant signage, repair of fixing points, and repair of hardstand damage. | Patching needed on the facade, pylon sign or driveway once signage and bollards come out. |
Asbestos in Older Industrial Buildings
Many Sydney warehouses and factories were built before asbestos was banned in Australia at the end of 2003. Roof sheeting, wall cladding, eaves, pipe lagging and old vinyl floors can all contain it. Removing fitout that is fixed to these materials can disturb them.
Under NSW work health and safety law, a workplace where asbestos is likely to be present must have an asbestos register. Ask the landlord or building manager for it before any strip-out starts. If the make good will disturb materials listed on it, the removal needs a licensed contractor. Our friable vs non-friable asbestos guide explains which licence applies.
Contamination at the End of an Industrial Lease
Some industrial leases require the tenant to hand the site back free of any contamination caused during the lease. Others ask for an environmental report at exit. Both are common where the tenant has stored fuel, chemicals or waste on site.
Your best protection is a baseline report from the start of the lease. Without one, it is hard to show that contamination was already in the ground before you moved in. If you do not have one, talk to your solicitor and an environmental consultant well before expiry. The final inspection is too late.
Why Industrial Make Good Takes Longer
The office timeline above assumes partitions, ceilings and carpet. A warehouse or factory adds steps that often have to happen one after another:
- Racking and mezzanine removal needs plant, crews and sometimes a crane.
- Every service to plant must be isolated and certified before removal starts.
- Slab repairs and resealing need time to cure before the inspection.
- Asbestos removal needs a clearance inspection before other trades can go back into that area.
- Contamination, if found, can add weeks while it is assessed.
Start earlier than you would for an office. On larger industrial sites, getting the scope priced 6 to 12 months before expiry gives you room to deal with what turns up.
We handle warehouse and factory make goods, including mezzanine and plant removal, asbestos removal and concrete removal. See our defit and make good services and industrial demolition services.
Handling the Final Inspection and Managing Disputes
What to Prepare Before the Inspection
Prepare a complete documentation pack before the landlord’s representative arrives. This should include photographs of all completed works, contractor invoices and sign-off records, any required services isolation certificates, and as-built drawings if the scope included services work. This is your evidence file. If a dispute arises, these documents are what you rely on.
How to Present the Site
Present the tenancy in the same order the schedule of dilapidations listed items. Walk through it methodically with the landlord’s representative. For each item they flagged, show the completed work or the evidence that the item was pre-existing or not your obligation. A structured walkthrough is harder to dispute than a general impression.
What to Contest and How
If the landlord’s representative raises items at inspection that you dispute, do not agree verbally. Take notes. After the inspection, respond in writing with your position on each disputed item, the specific lease clause you are relying on, and the supporting evidence. Evidence that supports a successful contest includes lease commencement condition report photos, base building drawings confirming an item is base building not fitout, and the lease clause itself where the obligation claimed is not actually in the document.
The NCAT Pathway
For retail leases under the NSW Retail Leases Act 1994, a dispute usually has to go to mediation through the NSW Small Business Commissioner first. If mediation does not resolve it, the dispute can then be referred to the NSW Civil and Administrative Tribunal (NCAT) for a hearing. For non-retail commercial leases, disputes typically proceed through the courts depending on the amount in dispute. In both cases, engage a commercial property solicitor before taking any formal steps. The cost of getting the process wrong can exceed the cost of the original dispute.
What Landlords Cannot Claim
Even where a breach exists, a landlord’s recovery is not uncapped. Claims are typically limited to the reasonable cost of rectification and any proven financial loss directly caused by the breach. Landlords cannot claim betterment, meaning they cannot require you to fund an upgrade to a higher standard than what existed before your tenancy. They also cannot claim for loss of rent during a rectification period unless the lease specifically provides for it. Knowing these limits matters when evaluating whether to accept a claim or contest it.
General information only. This article explains make good obligations in NSW in general terms. It is not legal advice. Every lease is different, so speak to a commercial property solicitor about your own lease before you respond to a schedule of dilapidations or take any step in a dispute.
Not Sure What Your Make-Good Clause Actually Requires?
Our team can review your lease scope, walk through the dilapidations schedule with you, and give you a clear picture of what the make-good work involves, how long it will take, and what it will cost. Get ahead of your expiry date before the timeline gets tight.
Frequently Asked Questions
Disclaimer: The information in this article is based on research and the professional experience of the Get It Away Demolition and Excavations team. Nothing in this article constitutes legal advice. Make-good obligations vary significantly between individual leases, building types, and commercial arrangements. For advice specific to your lease, engage a qualified commercial property solicitor. Cost figures reflect general Sydney market conditions as of 2025 and will vary based on tenancy size, scope, and contractor pricing.
