Demolition Checklist Sydney Pre Demolition Preparation Guide

This week decides whether demolition starts on time or gets pushed. The three most common day-one delays are utilities not confirmed off, site access blocked, and paperwork missing on the morning the crew arrives. This checklist prevents all three. Work through it from Monday to Friday and you will be ready.

Key Takeaways

  • Confirming utilities are off is different from confirming your booking. You need physical completion, not a scheduled date.
  • Standard demolition excavators require 3.5m clear access width. Measure it. Do not estimate it.
  • Any tree you want to keep needs a protection zone installed before the first machine arrives, not after.
  • The 48-hour knock on the neighbour’s door is different from the formal 2-week notice. This one is logistics, not relationship management.
  • Day-zero has a five-point agenda. Walk through it with the site supervisor before a single wall comes down.
  • Four documents must be physically on site on day one. If any are missing, work cannot legally commence.

Monday: Utility Confirmation

There is a critical difference between a utility abolishment being booked and it being done. A booking is a future intention. A completion is a fact. You need the fact confirmed before your start date, not the intention.

Make these calls on Monday. For each one, the question is not “Is my request in the system?” It is: “Has the abolishment been physically completed and recorded on your end?” Ask for a reference number or completion notice confirming the work is done.

Electricity: Ausgrid or Endeavour Energy

Ausgrid covers eastern, southern, and northern Sydney. Endeavour Energy covers western Sydney, the Hills District, Blue Mountains, and Illawarra. Only a Level 2 ASP (Accredited Service Provider) electrician can arrange permanent electricity abolishment. The abolishment involves physically removing the service line and meter. Typical lead time is 20 to 30 business days from the original request.

Call your Level 2 electrician and ask: “Has the physical disconnection been completed and recorded with Ausgrid/Endeavour Energy?” Ask for the service order completion reference. If they tell you it is still pending and your start date is this week, this is an escalation. Ask your electrician to contact the distributor directly to expedite. Do not wait.

Red flag: If electricity abolishment is not confirmed complete by Thursday, your start date is at risk. Push the escalation now, not Friday morning.

Gas: Jemena

Jemena is the gas distribution network across most of NSW. The abolishment process works through your gas retailer, not Jemena directly. Your retailer raises a service order, and Jemena sends a field technician to remove the meter and isolate the service at the mains. Jemena targets 20 business days for gas meter removals.

Call your gas retailer and ask: “Has Jemena completed the meter removal and mains isolation at my property? Can you confirm the completion date and provide a reference number?” If you cannot get confirmation from the retailer, call Jemena Customer Service NSW directly on 1300 137 078.

Red flag: Jemena is explicit that customers should not book demolition until the gas abolishment is physically complete. If your meter is still in place, demolition cannot start safely.

Water and Sewer: Sydney Water

A licensed plumber must cap the sewer line to prevent demolition debris from entering the Sydney Water system. This work requires Sydney Water approval and a licensed plumber. Call your plumber and ask: “Has the sewer capping been completed and has Sydney Water issued confirmation?” Ask for the job completion certificate or Sydney Water reference number.

Telecommunications: nbn Co

NBN connection abolishment is arranged through your internet service provider, who lodges the request with nbn Co. This involves disconnection of the service and removal of any nbn infrastructure at the premises. Call your internet provider and ask: “Has the nbn service abolishment at my address been physically completed?” Get a reference number. Your contractor will also need to know whether any overhead nbn lines cross the demolition site.

For the full utility abolishment booking process and lead times, see our 12-week knockdown rebuild guide. That guide covers how to book. This checklist covers how to confirm the booking is done.

Tuesday: Site Access Preparation

Blocked access on day one does not just delay the start. It may mean the crew cannot commence at all and you are charged a mobilisation fee. See our guide on what drives demolition costs in Sydney before you confirm your start date. Walk the access route yourself this week.

Minimum Clearance Widths

Standard demolition excavators in the 8 to 30 tonne range used on full house demolitions are 2.5 to 3.5 metres wide. You need a minimum 3.5 metres clear width for a standard demolition excavator to access the site without risk of damage or delay. Mini plant, used on tight-access sites, requires a minimum 2.5 metres. Confirm with your contractor which machine size is coming and measure your access accordingly. Do not estimate it. Use a tape measure.

The Access Checklist

  • Cars and trailers. Move every vehicle off the property and from the street-access route. If neighbours have vehicles near the access point, give them a heads-up the night before.
  • Bins. Council bins, garden waste bags, skip bins from previous work. All need to be moved off the access path.
  • Pot plants, garden furniture, children’s equipment. These are the most commonly missed items. Walk the full access route from the street to the back of the property and remove everything.
  • Side path clearance. Items stored on side paths are the single most common unexpected blockage on day one. Hoses, stored timber, garden tools, Weber BBQs, clotheslines. Clear all of it.
  • Gates and locks. The contractor needs unrestricted access from the moment they arrive. Arrange spare key or code handover in advance. Do not leave a locked gate for a crew that has a 7am start.
  • Skip bin position. Confirm the bin placement with your contractor this week. The bin must not block machine access or truck turning. If it requires a road occupancy permit, confirm that permit is in hand.

Measure the narrowest point of the access route. Write it down. Text it to your contractor today so there are no surprises on the morning.

Wednesday: Protecting What You Are Keeping

If it is not on a written protection list, assume the crew will demolish it. That is not a criticism of demolition crews. It is how scope works. Your job this week is to make the protection list explicit and physical.

Mature Trees: Tree Protection Zones

Any tree you want to retain needs a Tree Protection Zone (TPZ) installed before the first machine arrives. Under Australian Standard AS 4970-2009, the TPZ radius is calculated by multiplying the tree’s trunk diameter at breast height (DBH, measured 1.4 metres above ground) by 12. Minimum TPZ radius is 2 metres, maximum is 15 metres.

Example: A tree with a 40cm trunk diameter at 1.4m height has a TPZ radius of 40cm x 12 = 480cm, or 4.8 metres from the centre of the trunk.

Mark the TPZ with orange mesh safety fencing installed on star pickets. This is the minimum physical standard. Machines must not enter this zone. Confirm with your contractor in writing that the TPZ is a no-go zone for all equipment, and attach a written note to the fencing with the tree details and the retained tree status.

Fences, Items to Salvage, and Garden Beds

  • Boundary fences. Confirm in writing with your contractor which fences are to remain and which are being demolished. Photograph each retained fence this week and send the photos to your contractor with a note confirming its status.
  • Items to salvage. Mark every item you want saved with bright orange or yellow tape. Give the site supervisor a written list the morning of day one. If it is not on the list, do not assume it will be saved. Items commonly lost in demolition include letterboxes, feature pavers, outdoor light fittings, and clothesline frames.
  • Garden beds and topsoil. If specific garden beds are to be protected or topsoil is to be stockpiled for the rebuild, this must be communicated explicitly to the supervisor on day one. Note the location and what action you want taken.

The principle is simple. If it is not explicitly on a written protection list that you hand to the supervisor at the start of day one, assume it will be demolished.

Thursday: Pets, Family, and the Noise Reality

Animals

Dogs and cats must be kept off site for the full duration of demolition. This is not optional. Demolition dust is harmful to animals and machinery noise causes significant distress. Arrange boarding, a friend’s place, or keep them confined indoors well away from the demolition area.

If you know neighbours have dogs that back onto the demolition site, a courtesy call is worth making. It is not a legal requirement. But a stressed dog barking for three days at noise and machinery is the kind of thing that turns a good neighbourly relationship into a complaint.

Children and Dust

Demolition noise at 10 metres runs 85 to 95 decibels for typical excavation activity. That is louder than a lawn mower and comparable to standing near busy traffic. Children should not be on or near the site during demolition.

The noisiest days will typically be slab removal and concrete breaking. These are the highest-noise, highest-dust events. On those specific days, keep children and anyone with respiratory sensitivities well clear of the site and immediately downwind areas.

Demolition dust is not ordinary construction dust. For pre-1987 properties, it may contain asbestos fibres. Even on newer properties, fine concrete and brick dust is a real health risk for children. A safe distance is at least 50 metres from active demolition, and indoors with windows closed on high-dust days.

Friday Morning: The 48-Hour Neighbour Notice

This is not the formal two-week written notification you sent earlier. That was about the relationship. This is logistics.

Knock on the door of each immediately adjoining neighbour on Friday. Keep it brief. Something like: “We start Monday. The contractor’s name is [Name] and the direct site number is [number]. There will be some parking disruption on the street for the first few days. Trucks and the skip bin. Just wanted to give you a heads-up.”

Leave the contractor’s mobile number, not just yours. Direct access to the site supervisor reduces escalations and means small concerns get handled at the right level without going straight to a complaint.

For the full neighbour communication approach and dispute prevention strategy, see our neighbour management guide.

Day One: The Five-Point Walkthrough Agenda

Before the first machine moves, walk the site with the supervisor and cover these five items in order. Do not skip any of them. This conversation takes fifteen minutes and prevents problems that would otherwise take days to fix.

1

Walk the Boundary and Confirm Demolition Limits

Walk the full perimeter of the site with the supervisor and physically point to every structure that is to remain. Fences. Trees. Letterboxes. Retaining walls. Anything you have on your protection list, show them in person. Do not assume the plans or contract scope are sufficient. Point. Confirm. Move on.

2

Confirm Tree Protection Zones Are Installed

Walk to each retained tree. Confirm the orange mesh fencing is in position at the correct TPZ radius. Confirm the supervisor has been briefed that these zones are no-go areas for all plant and machinery. If any TPZ fencing is not yet in place, it must be installed before equipment moves.

3

Confirm Skip Bin Position and Machine Access Route

Walk the full machine access route from the street to the structure. Confirm the skip bin is positioned so it does not block machine movement or truck turning. If the contractor plans to bring a second machine or a truck for waste, confirm the turning radius at the tightest point is workable. Better to identify this now than when a truck is stuck blocking the street.

4

Confirm Approvals and Paperwork Are on Site

Ask the supervisor to show you the site file. The following four documents must be physically present on site before work commences. If any are missing, work cannot legally begin.

  • DA or CDC approval document: the original stamped approval, not just a copy on someone’s phone.
  • Demolition permit or complying development certificate: the operative approval that authorises the demolition specifically.
  • Asbestos survey report: required for any pre-1987 structure. Must be on site and accessible to all workers before demolition begins.
  • Site safety plan / Safe Work Method Statement (SWMS): the contractor’s documented safety procedures for the demolition. This is a legal requirement under the Work Health and Safety Act 2011 (NSW) for high-risk construction work.
5

Exchange Emergency Contacts and Agree the Communication Protocol

Confirm: your mobile number. The supervisor’s direct mobile. Who to call in an emergency. What constitutes an emergency versus a normal site event. And agree the update schedule: daily SMS on active demolition days by 5pm, and a brief weekly call. This takes three minutes to agree and prevents a week of anxiety about what is happening on site.

Related guides in this series:

All approvals should be finalised before this checklist. See our NSW demolition approvals guide for DA and CDC requirements.

For the full utility abolishment booking process and lead times, see our 12-week knockdown rebuild guide.

Want to Make Sure Nothing Gets Missed?

Get It Away manages the pre-start process across every project. Utilities confirmed, access cleared, protection zones in place, paperwork on site. See our full demolition services across Sydney.

Check Out Our Services

Frequently Asked Questions

Call each utility authority directly and ask whether the physical abolishment has been completed and recorded. For electricity, contact your Level 2 ASP electrician and ask for the Ausgrid or Endeavour Energy service order completion reference. For gas, call your retailer and ask whether Jemena has completed the meter removal. For water and sewer, ask your plumber for the Sydney Water capping completion certificate. For nbn, call your internet provider and ask for the abolishment reference. A booking confirmation is not enough. You need completion confirmation.
Standard demolition excavators in the 8 to 30 tonne range used on full house demolitions are 2.5 to 3.5 metres wide. You need a minimum clear width of 3.5 metres for this class of machine. Mini plant used on tight-access sites requires a minimum 2.5 metres. Confirm with your contractor which machine size is coming and measure the narrowest point of your access route. Do not estimate it.
Under Australian Standard AS 4970-2009, the TPZ radius equals the tree’s trunk diameter at breast height (measured at 1.4 metres above ground) multiplied by 12. The minimum TPZ radius is 2 metres and the maximum is 15 metres. For example, a tree with a 30cm trunk diameter has a TPZ radius of 3.6 metres from the centre of the trunk. Mark the zone with orange mesh safety fencing before any plant arrives on site.
Four documents must be physically present on site before work commences: the DA or CDC approval document, the demolition permit or complying development certificate, the asbestos survey report for any pre-1987 structure, and the contractor’s Safe Work Method Statement (SWMS) for the demolition work. If any of these are missing on day one, legally work cannot begin.
If utilities are not confirmed physically complete by Thursday of the week before your start date, your start date is at risk. Do not assume the issue will resolve itself. Escalate immediately. For electricity, ask your Level 2 electrician to contact Ausgrid or Endeavour Energy directly and request an expedited completion. For gas, call Jemena Customer Service NSW on 1300 137 078 and explain the demolition date. Both networks deal with expedited requests regularly. Early escalation on Thursday gives you a chance of resolution by Monday. Waiting until Friday does not.
Yes. Your internet service provider must lodge an abolishment request with nbn Co to disconnect the service and arrange removal of any nbn infrastructure at the premises. Call your provider and ask whether the abolishment has been completed. Also confirm with your contractor whether any overhead nbn service lines cross the demolition area, as these must be cleared before work begins in that zone.
Typical demolition excavation activity runs 85 to 95 decibels at 10 metres. The loudest events are slab removal and concrete breaking. Children and anyone with respiratory sensitivities should stay at least 50 metres from active demolition and remain indoors with windows closed on high-dust days. For pre-1987 properties where asbestos may be present, these precautions are not optional.
The most commonly lost items in residential demolitions are letterboxes, feature pavers and stepping stones, outdoor light fittings, clothesline frames, garden tap fittings, and items stored in side paths or under decks. The best prevention is a written list handed to the supervisor at the start of day one, with each item physically marked with bright tape. If it is not on the list and not marked, it is at risk.
Yes, for the day-zero walkthrough. You do not need to stay for the full day, but being present at the start to walk through the five-point agenda with the site supervisor is worth thirty minutes of your time. It confirms demolition limits, protection zones, access, paperwork, and communication in person. Issues identified at this point take minutes to resolve. The same issues identified after the first wall comes down take days.

Ready to Start With Confidence?

Get It Away works through every item on this checklist with you before day one. See our full demolition services across Sydney or get in touch for a free quote.

Disclaimer: The information in this article is based on publicly available research, current NSW legislation, utility provider guidelines, and the views of the Get It Away team at the time of writing. It is intended as general action guidance only and does not constitute legal, technical, or contractual advice. Utility provider processes, lead times, and contact details change. Always verify current requirements directly with Ausgrid, Endeavour Energy, Jemena, Sydney Water, nbn Co, and your local council before relying on any specific details. If you have questions about your specific project, please reach out to us directly or consult a qualified professional.